| United States. Department of the Treasury. Procurement Division - 1943 - 414 lapas
...to be furnished are to be specially manufactured in accordance with drawings and specifications, the contracting officer may at any time, by a written...notice to the sureties, make changes in the drawings or specifications, except Federal Specifications. Changes as to shipment and packing of all supplies... | |
| 1949 - 906 lapas
...detail drawings and other information as he may consider necessary, unless otherwise provided. ABT. 8. Changes. The contracting officer may at any time,...notice to the sureties, make changes in the drawings and/or specifications of this contract and within the general scope thereof. If such changes cause... | |
| 1949 - 738 lapas
...detail drawings and other information as he may consider necessary, unless otherwise provided. Any. 3. Changes. The contracting officer may at any time,...notice to the sureties, make changes in the drawings and/or specifications of this contract and within the general scope thereof. If such changes cause... | |
| 1967 - 452 lapas
...Definitions. Insert the clause set forth in $ 1007.4205-1. § 1007.4207-3 Changes. CHANGES (OCT. 1987) The Contracting Officer may at any time, by a written...without notice to the sureties, make changes In the drawing of specifications of this contract and within the general scope thereof. If such changes cause... | |
| 1964 - 432 lapas
...provided in this contract, tin1 term "subcontracts" includes purchase orders under this contract. 2. CHANGES The Contracting Officer may at any time, by...and without notice to the sureties, make changes, within the general scope of this cpn tract, in any OIK- or more of the following: (i) Drawings, designs,... | |
| 1983 - 1104 lapas
...foregoing clause or the provisions of this Regulation. 7.103-2 Changes. CHANGES (SEPTEMBER 1962) The Contracting Officer may at any time, by a written...and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following: (i) Drawings, designs,... | |
| 1969 - 752 lapas
...provisions of this subchapter. [27 PR 3450. Apr. 11. 1962] § 7.103-2 Changes. CHANGES (JAM. 1958) The Contracting Officer may at any time, by a written...and without notice to the sureties, make changes, within the general scope of this contract, In any one or more of the following: (1) Drawings, designs,... | |
| 1966 - 968 lapas
...provided. § 7.602-3 Changes. CHANGES (JUNE 1964) The Contracting Officer may, at any time, by written order, and without notice to the sureties, make changes...the drawings and/ or specifications of this contract if within its general scope. If such changes cause an Increase or decrease in the Contractor's cost... | |
| 1980 - 582 lapas
...embalming process on a certificate furnished by the Contracting Officer. (End of clause) § 12-7.5001-29 Changes. The Contracting Officer may at any time, by a written order, and without notice to the sureties, if any, make changes in or additions to specifications, issue additional instructions, require... | |
| 1979 - 1304 lapas
...Definitions. Insert the clause set forth in § 17.102-1. [40 FR 44140, Sept. 25, 1975] § 1-7.703-2 Changes. CHANGES The Contracting Officer may, at any time, by a written order and without notice to the sureties, if any, make changes within the general scope of the contract in any one or more of the following:... | |
| |