...intended type of contract : Design will be accomplished under negotiated architect-engineer contract Construction and procurement will be accomplished...contracts awarded on the basis of competitive bids. DORMITORIES, NEVADA TEST SITE Mr. ABBADESSA. This facility represents a unique capability in our weapons... | |
| United States. Congress. Joint Committee on Atomic Energy - 1965 - 850 lapas
...intended type of contract Design will be accomplished under negotiated architect-engineer contract. Construction and procurement will be accomplished...contracts awarded on the basis of competitive bids. CORRESPONDENCE ON FLOOD CONTROL PROJECT — KANSAS CITY DEPARTMENT OF THE ARMY, OFFICE OF THE CHIEF... | |
| United States. Congress. Joint Committee on Atomic Energy - 1968 - 1014 lapas
...will be on the basis of a negotiated architect-engineer contract. To the extent feasible, construction will be accomplished by fixed-price contracts awarded on the basis of competitive bidding. 12. Incorporation of Fallout Shelters in Future Federal Buildings: A fallout shelter sized... | |
| United States. Congress. Joint Committee on Atomic Energy - 1968 - 948 lapas
...will be on the basis of a negotiated architect-engineer contract. To the extent feasible, construction will be accomplished by fixed-price contracts awarded on the basis of competitive bidding. 12. Incorporation of Fallout Shelters in Future Federal Buildings: A fallout shelter sized... | |
| United States. Congress. Joint Committee on Atomic Energy - 1969 - 860 lapas
...All Major Contractors; Design will be by the operator and a negotiated architect-engineer contract. To the extent feasible, construction and procurement will be accomplished by fixedprice contracts and subcontracts awarded on the basis of competitive bids. Participants : Not applicable. Cost Comparisons:... | |
| United States. Congress. Joint Committee on Atomic Energy - 1969 - 872 lapas
...intended that the design work will be awarded on the basis of negotiated architect -engineer contracts. To the extent feasible, construction and procurement will be accomplished by fixed-price contracts (warded on the basis of competitive bidding. Participants: Not applicable. Cost Comparisons: No comparable... | |
| United States. Congress. Joint Committee on Atomic Energy - 1969 - 880 lapas
...All Malor Contractors: Design will be by the operator and a negotiated architect-engineer contract. To the extent feasible, construction and procurement will be accomplished by fixedprice contracts and subcontracts awarded on the basis of competitive bids. Participants: Not applicable. Cost Comparisons:... | |
| United States. Congress. Joint Committee on Atomic Energy - 1972 - 976 lapas
...used in selecting all Major Contractors Design will be by a negotiated architect-engineer contract. Construction and procurement will be accomplished...fixed-price contracts, awarded on the basis of competitive bidding. Alternatives The alternative to constructing the proposed addition is a long-term lease of... | |
| United States. Congress. Joint Committee on Atomic Energy - 1972 - 936 lapas
...Selecting all Major Contractors Design will be accomplished by negotiated architect -engineer contracts. To the extent feasible, construction and procurement will be accomplished by fixed-price contracts and subcontracts awarded on the basis of competitive bids. Participants Not applicable. This project... | |
| |