" That .the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence... "
Cases Decided in the Court of Claims of the United States - 137. lappuse
autors: United States. Court of Claims - 1943
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 111. sējums

United States. Court of Claims - 1948 - 886 lapas
...liquidated damages for delay in completing the work and contained the following proviso : Provided, That the right of the contractor to proceed shall...unforeseeable causes beyond the control and without the fault or negligence of the con552 Reporter's Statement of the Case tractor, including, but not restricted...
Pilnskats - Par šo grāmatu

Decisions of the Comptroller General of the United States, 29. sējums

United States. General Accounting Office - 1950 - 710 lapas
...the provisions of article 9 of the contract proper. The said article 9 provided, in pertinent part, as follows: * * * That the right of the contractor...because of any delays in the completion of the work duo to unforeseeable causes beyond the control and without the fault or negligence of the contractor,...
Pilnskats - Par šo grāmatu

Decisions of the Comptroller General of the United States, 7. sējums

United States. General Accounting Office - 1928 - 1012 lapas
...accompanying papers and the contractor and his sureties shall be liable for the amount thereof: Provided, That the right of the contractor to proceed shall...work due to unforeseeable causes beyond the control mid without the fault or negligence of the contractor, including, but not restricted to, acts of God,...
Pilnskats - Par šo grāmatu

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - 1928 - 228 lapas
...prescribed contract forms for use throughout the executive branch, which contain the following provision : " The right of the contractor to proceed shall not be...of any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including,...
Pilnskats - Par šo grāmatu

Decisions of the Comptroller General of the United States, 8. sējums

United States. General Accounting Office - 1929 - 804 lapas
...accompanying papers and the contractor and his sureties shall be liable for the amount thereof: Provided, That the right of the contractor to proceed shall not be terminated or the contractor chargel with liquidated damages because of any delays in the completion of the work due to unforeseeable...
Pilnskats - Par šo grāmatu

Establish Uniform Requirements for Government Contracts. Hearing ... on H.R. 255

United States. U.S. Congress. House. Committee on judiciary - 1932 - 234 lapas
...proposition set forth in article 9 of the standard Government form of contract as the latter distinctly says: That the right of the contractor to proceed shall...unforeseeable causes beyond the control and without the fault or negligence of the contractor, etc. According to the Government contract form this matter of...
Pilnskats - Par šo grāmatu

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 lapas
...materials, appliances, and plant as may be on the site of the work and necessary therefor; provided, that the right of the contractor to proceed shall not be terminated under this article because of any delays in the completion of the work due to causes beyond the control...
Pilnskats - Par šo grāmatu

Decisions of the Comptroller General of the United States, 14. sējums

United States. General Accounting Office - 1935 - 1044 lapas
...accompanying papers and the contractor and his sureties shall be liable for the amount thereof: Provided, That the right of the contractor to proceed shall...of any delays in the completion of the work due to unforeseeaMe causes beyond the control aud witlu ut the fault or negligence of the contractor, including,...
Pilnskats - Par šo grāmatu

Taking the Profits Out of War: Hearings Before the Committee on Military ...

United States. Congress. House. Committee on Military Affairs - 1935 - 990 lapas
...shall be liable for the amount thereof : Pi'ovided, That the right of the contiaetor to proceed simall not be terminated or the contractor charged with liquidated...unforeseeable causes beyond the control and without the fault or neglIgence of the contractor “as determined by the contractiimg officer: Provkled further,...
Pilnskats - Par šo grāmatu

Taking the Profits Out of War: Hearings Before the Committee on Military ...

United States. Congress. House. Committee on Military Affairs - 1935 - 812 lapas
...accompanying papers, and the eontractor and his sureties shall he liable for the amount thereof : Provided. p becnuse of any delays In the completion of the work due to unforeseeable causes beyond the control...