ment, the terms and conditions shall be included in the final order. In the case of an order under section 824i of this title, if the parties fail to agree within the time set by the Commission or if the Commission does not approve any such agreement, the Commission shall prescribe such terms and conditions and include such terms and conditions in the final order.

(B) In the case of any order applied for under section 824j of this title, if the parties fail to agree within the time set by the Commission, the Commission shall prescribe such terms and conditions in the final order.

(d) Statement of reasons for denial

If the Commission does not issue any order applied for under section 824i or 824j of this title, the Commission shall, by order, deny such application and state the reasons for such denial.

(e) Savings provisions

(1) No provision of section 824i, 824j, 824m of this title, or this section shall be treated as requiring any person to utilize the authority of any such section in lieu of any other authority of law. Except as provided in section 824i, 824j, 824m of this title, or this section, such sections shall not be construed as limiting or impairing any authority of the Commission under any other provision of law.

(2) Sections 8241, 824j, 8247, 824m of this title, and this section, shall not be construed to modify, impair, or supersede the antitrust laws. For purposes of this section, the term "antitrust laws" has the meaning given in subsection (a) of the first sentence of section 12 of title 15, except that such term includes section 45 of title 15 to the extent that such section relates to unfair methods of competition.

(f) Effective date of order; hearing; notice; review

(1) No order under section 824i or 824j of this title requiring the Tennessee Valley Authority (hereinafter in this subsection referred to as the "TVA") to take any action shall take effect for 60 days following the date of issuance of the order. Within 60 days following the issuance by the Commission of any order under section 824i or of section 824j of this title requiring the TVA to enter into any contract for the sale or delivery of power, the Commission may on its own motion initiate, or upon petition of any aggrieved person shall initiate, an evidentiary hearing to determine whether or not such sale or delivery would result in violation of the third sentence of section 15d(a) of the Tennessee Valley Authority Act of 1933 (16 U.S.C. 831n-4), hereinafter in this subsection referred to as the TVA Act [16 U.S.C. 831 et seq.).

(2) Upon initiation of any evidentiary hearing under paragraph (1), the Commission shall give notice thereof to any applicant who applied for and obtained the order from the Commission, to any electric utility or other entity subject to such order, and to the public, and shall promptly make the determination referred to in paragraph (1). Upon initiation of such hearing, the Commission shall stay the effectiveness of the order under section 824i or 824j of this title until whichever of the following dates is applicable

(A) the date on which there is a final determination (including any judicial review thereof under paragraph (3)) that no such violation would result from such order, or

(B) the date on which a specific authorization of the Congress (within the meaning of the third sentence of section 15d(a) of the TVA Act [16 U.S.C. 831n-4(a)]) takes effect.

(3) Any determination under paragraph (1) shall be reviewable only in the appropriate court of the United States upon petition filed by any aggrieved person or municipality within 60 days after such determination, and such court shall have jurisdiction to grant appropriate relief. Any applicant who applied for and obtained the order under section 824i or 824j of this title, and any electric utility or other entity subject to such order shall have the right to intervene in any such proceeding in such court. Except for review by such court (and any appeal or other review by an appellate court of the United States), no court shall have jurisdiction to consider any action brought by any person to enjoin the carrying out of any order of the Commission under section 824i or section 824j of this title requiring the TVA to take any action on the grounds that such action requires a specific authorization of the Congress pursuant to the third sentence of section 15d(a) of the TVA Act [16 U.S.C. 831n-4(a)].

(g) Prohibition on orders inconsistent with retail marketing areas

No order may be issued under this chapter which is inconsistent with any State law which governs the retail marketing areas of electric utilities.

(h) Prohibition on mandatory retail wheeling and sham wholesale transactions

No order issued under this chapter shall be conditioned upon or require the transmission of electric energy:

(1) directly to an ultimate consumer, or

(2) to, or for the benefit of, an entity if such electric energy would be sold by such entity directly to an ultimate consumer, unless:

(A) such entity is a Federal power marketing agency; the Tennessee Valley Authority; a State or any political subdivision of a State (or an agency, authority, or instrumentality of a State or a political subdivision); a corporation or association that has ever received a loan for the purposes of providing electric service from the Administrator of the Rural Electrification Administration under the Rural Electrification Act of 1936 [7 U.S.C. 901 et seq.]; a person having an obligation arising under State or local law (exclusive of an obligation arising solely from a contract entered into by such person) to provide electric service to the public; or any corporation or association which is wholly owned, directly or indirectly, by any one or more of the foregoing; and

(B) such entity was providing electric service to such ultimate consumer on October 24, 1992, or would utilize transmission or distribution facilities that it owns or con

trols to deliver all such electric energy to such electric consumer.

Nothing in this subsection shall affect any authority of any State or local government under State law concerning the transmission of electric energy directly to an ultimate consumer. (i) Laws applicable to Federal Columbia River Transmission System

(1) The Commission shall have authority pursuant to section 824i of this title, section 824j of this title, this section, and section 8241 of this title to (A) order the Administrator of the Bonneville Power Administration to provide transmission service and (B) establish the terms and conditions of such service. In applying such sections to the Federal Columbia River Transmission System, the Commission shall assure that

(i) the provisions of otherwise applicable Federal laws shall continue in full force and effect and shall continue to be applicable to the system; and

(ii) the rates for the transmission of electric power on the system shall be governed only by such otherwise applicable provisions of law and not by any provision of section 824i of this title, section 824j of this title, this section, or section 8241 of this title, except that no rate for the transmission of power on the system shall be unjust, unreasonable, or unduly discriminatory or preferential, as determined by the Commission.

(2) Notwithstanding any other provision of this chapter with respect to the procedures for the determination of terms and conditions for transmission service

(A) when the Administrator of the Bonneville Power Administration either (i) in response to a written request for specific transmission service terms and conditions does not offer the requested terms and conditions, or (ii) proposes to establish terms and conditions of general applicability for transmission service on the Federal Columbia River Transmission System, then the Administrator may provide opportunity for a hearing and, in so doing, shall

(I) give notice in the Federal Register and state in such notice the written explanation of the reasons why the specific terms and conditions for transmission services are not being offered or are being proposed;

(II) adhere to the procedural requirements of paragraphs (1) through (3) of section 839e(i) of this title, except that the hearing officer shall, unless the hearing officer becomes unavailable to the agency, make a recommended decision to the Administrator that states the hearing officer's findings and conclusions, and the reasons or basis thereof, on all material issues of fact, law, or discretion presented on the record; and

(III) make a determination, setting forth the reasons for reaching any findings and conclusions which may differ from those of the hearing officer, based on the hearing record, consideration of the hearing officer's recommended decision, section 824j of

this title and this section, as amended by the Energy Policy Act of 1992, and the provisions of law as preserved in this section; and

(B) if application is made to the Commission under section 824j of this title for transmission service under terms and conditions different than those offered by the Administrator, or following the denial of a request for transmission service by the Administrator, and such application is filed within 60 days of the Administrator's final determination and in accordance with Commission procedures, the Commission shall

(i) in the event the Administrator has conducted a hearing as herein provided for (I) accord parties to the Administrator's hearing the opportunity to offer for the Commission record materials excluded by the Administrator from the hearing record, (II) accord such parties the opportunity to submit for the Commission record comments on appropriate terms and conditions, (III) afford those parties the opportunity for a hearing if and to the extent that the Commission finds the Administrator's hearing record to be inadequate to support a decision by the Commission, and (IV) establish terms and conditions for or deny transmission service based on the Administrator's hearing record, the Commission record, section 824j of this title and this section, as amended by the Energy Policy Act of 1992, and the provisions of law as preserved in this section, or

(ii) in the event the Administrator has not conducted a hearing as herein provided for, determine whether to issue an order for transmission service in accordance with section 824j of this title and this section, including providing the opportunity for a hearing.

(3) Notwithstanding those provisions of section 8257(b) of this title which designate the court in which review may be obtained, any party to a proceeding concerning transmission service sought to be furnished by the Administrator of the Bonneville Power Administration seeking review of an order issued by the Commission in such proceeding shall obtain a review of such order in the United States Court of Appeals for the Pacific Northwest, as that region is defined by section 839a(14) of this title.

(4) To the extent the Administrator of the Bonneville Power Administration cannot be required under section 824j of this title, as a result of the Administrator's other statutory mandates, either to (A) provide transmission service to an applicant which the Commission would otherwise order, or (B) provide such service under rates, terms, and conditions which the Commission would otherwise require, the applicant shall not be required to provide similar transmission services to the Administrator or to provide such services under similar rates, terms, and conditions.

(5) The Commission shall not issue any order under section 824i of this title, section 824j of

this title, this section, or section 8241 of this title requiring the Administrator of the Bonneville Power Administration to provide transmission service if such an order would impair the Administrator's ability to provide such transmission service to the Administrator's power and transmission customers in the Pacific Northwest, as that region is defined in section 839a(14) of this title, as is needed to assure adequate and reliable service to loads in that region.

(j) Equitability within territory restricted electric systems

With respect to an electric utility which is prohibited by Federal law from being a source of power supply, either directly or through a distributor of its electric energy, outside an area set forth in such law, no order issued under section 824j of this title may require such electric utility (or a distributor of such electric utility) to provide transmission services to another entity if the electric energy to be transmitted will be consumed within the area set forth in such Federal law, unless the order is in furtherance of a sale of electric energy to that electric utility: Provided, however, That the foregoing provision shall not apply to any area served at retail by an electric transmission system which was such a distributor on October 24, 1992, and which before October 1, 1991, gave its notice of termination under its power supply contract with such electric utility.

(k) ERCOT utilities

(1) Rates

Any order under section 824j of this title requiring provision of transmission services in whole or in part within ERCOT shall provide that any ERCOT utility which is not a public utility and the transmission facilities of which are actually used for such transmission service is entitled to receive compensation based, insofar as practicable and consistent with subsection (a) of this section, on the transmission ratemaking methodology used by the Public Utility Commission of Texas. (2) Definitions

For purposes of this subsection

(A) the term “ERCOT” means the Electric Reliability Council of Texas; and

(B) the term "ERCOT utility" means a transmitting utility which is a member of ERCOT.

(June 10, 1920, ch. 285, pt. II, § 212, as added Pub. L. 95-617, title II, § 204(a), Nov. 9, 1978, 92 Stat. 3138; amended Oct. 24, 1992, Pub. L. 102-486, title VII, § 722, 106 Stat. 2916.)

REFERENCES IN TEXT

The TVA Act, referred to in subsec. (f)(1), means act May 18, 1933, ch. 32, 48 Stat. 58, as amended, known as the Tennessee Valley Authority Act of 1933, which is classified generally to chapter 12A (§ 831 et seq.) of this title. For complete classification of this Act to the Code, see section 831 of this title and Tables.

The Rural Electrification Act of 1936, referred to in subsec. (h)(2)(A), is act May 20, 1936, ch. 432, 49 Stat. 1363, as amended, which is classified generally to chapter 31 ( 901 et seq.) of Title 7, Agriculture. For complete classification of this Act to the Code, see section 901 of Title 7 and Tables.

The Energy Policy Act of 1992, referred to in subsec. (1)(2)(A)(III), (B)(i), is Pub. L. 102-486, Oct. 24, 1992, 106 Stat. 2776. For complete classification of this Act to the Code, see Short Title note set out under section 13201 of Title 42, The Public Health and Welfare and Tables.

AMENDMENTS

1992-Subsec. (a). Pub. L. 102-486, § 722(1), added subsec. (a) and struck out former subsec. (a) which related to determinations by Commission.

Subsec. (b). Pub. L. 102-486, § 722(1), struck out subsec. (b) which required applicants for orders to be ready, willing, and able to reimburse parties subject to such orders.

Subsec. (e). Pub. L. 102-486, § 722(2), amended subsec. (e) generally. Prior to amendment, subsec. (e) related to utilization of interconnection or wheeling authority in lieu of other authority and limitation of Commission authority.

Subsecs. (g) to (k). Pub. L. 102-486, § 722(3), added subsecs. (g) to (k).

STATE AUTHorities; ConSTRUCTION

Nothing in amendment by Pub. L. 102-486 to be construed as affecting or intending to affect, or in any way to interfere with, authority of any State or local government relating to environmental protection or siting of facilities, see section 731 of Pub. L. 102-486, set out as a note under section 79 of Title 15, Commerce and Trade.

TRANSFER OF FUNCTIONS

The Federal Power Commission was terminated and its functions, personnel, property, funds, etc., were transferred to the Secretary of Energy (except for certain functions which were transferred to the Federal Energy Regulatory Commission) by sections 7151(b), 7171(a), 7172(a), 7291, and 7293 of Title 42, The Public Health and Welfare.

SECTION REFERRED TO IN OTHER SECTIONS This section is referred to in sections 824, 824a-3, 8241, 824j, 825n, 8250, 8250-1 of this title.

§ 8241. Information requirements

(a) Requests for wholesale transmission services Whenever any electric utility, Federal power marketing agency, or any other person generating electric energy for sale for resale makes a good faith request to a transmitting utility to provide wholesale transmission services and requests specific rates and charges, and other terms and conditions, unless the transmitting utility agrees to provide such services at rates, charges, terms and conditions acceptable to such person, the transmitting utility shall, within 60 days of its receipt of the request, or other mutually agreed upon period, provide such person with a detailed written explanation, with specific reference to the facts and circumstances of the request, stating (1) the transmitting utility's basis for the proposed rates, charges, terms, and conditions for such services, and (2) its analysis of any physical or other constraints affecting the provision of such services.

(b) Transmission capacity and constraints

Not later than 1 year after October 24, 1992, the Commission shall promulgate a rule requiring that information be submitted annually to the Commission by transmitting utilities which is adequate to inform potential transmission

customers, State regulatory authorities, and the public of potentially available transmission capacity and known constraints.

(June 10, 1920, ch. 285, pt. II, § 213, as added Oct. 24, 1992, Pub. L. 102-486, title VII, § 723, 106 Stat. 2919.)

STATE AUTHOrities; ConstRUCTION

Nothing in this section to be construed as affecting or intending to affect, or in any way to interfere with, authority of any State or local government relating to environmental protection or siting of facilities, see section 731 of Pub. L. 102-486, set out as a note under section 79 of Title 15, Commerce and Trade.

SECTION REFERRED TO IN OTHER SECTIONS This section is referred to in sections 824k, 825n, 8250, 8250-1 of this title; title 26 section 142.

§ 824m. Sales by exempt wholesale generators

No rate or charge received by an exempt wholesale generator for the sale of electric energy shall be lawful under section 824d of this title if, after notice and opportunity for hearing, the Commission finds that such rate or charge results from the receipt of any undue preference or advantage from an electric utility which is an associate company or an affiliate of the exempt wholesale generator. For purposes of this section, the terms "associate company" and "affiliate" shall have the same meaning as provided in section 79b(a) of title 15.

(June 10, 1920, ch. 285, pt. II, § 214, as added Oct. 24, 1992, Pub. L. 102-486, title VII, § 724, 106 Stat. 2920.)

STATE AUTHORITIES; CONSTRUCTION

Nothing in this section to be construed as affecting or intending to affect, or in any way to interfere with, authority of any State or local government relating to environmental protection or siting of facilities, see section 731 of Pub. L. 102-486, set out as a note under section 79 of Title 15, Commerce and Trade.

SECTION REFERRED TO IN OTHER SECTIONS

This section is referred to in sections 824k, 825n, 2850, 8250-1 of this title.

[blocks in formation]

Every licensee and public utility shall make, keep, and preserve for such periods, such accounts, records of cost-accounting procedures, correspondence, memoranda, papers, books, and other records as the Commission may by rules and regulations prescribe as necessary or appropriate for purposes of the administration of this chapter, including accounts, records, and memoranda of the generation, transmission, distribution, delivery, or sale of electric energy, the furnishing of services or facilities in connection therewith, and receipts and expenditures with respect to any of the foregoing: Provided,

however, That nothing in this chapter shall relieve any public utility from keeping any accounts, memoranda, or records which such public utility may be required to keep by or under authority of the laws of any State. The Commission may prescribe a system of accounts to be kept by licensees and public utilities and may classify such licensees and public utilities and prescribe a system of accounts for each class. The Commission, after notice and opportunity for hearing, may determine by order the accounts in which particular outlays and receipts shall be entered, charged, or credited. The burden of proof to justify every accounting entry questioned by the Commission shall be on the person making, authorizing, or requiring such entry, and the Commission may suspend a charge or credit pending submission of satisfactory proof in support thereof.

(b) Access to and examination by the Commission

The Commission shall at all times have access to and the right to inspect and examine all accounts, records, and memoranda of licensees and public utilities, and it shall be the duty of such licensees and public utilities to furnish to the Commission, within such reasonable time as the Commission may order, any information with respect thereto which the Commission may by order require, including copies of maps, contracts, reports of engineers, and other data, records, and papers, and to grant to all agents of the Commission free access to its property and its accounts, records, and memoranda when requested so to do. No member, officer, or employee of the Commission shall divulge any fact or information which may come to his knowledge during the course of examination of books or other accounts, as hereinbefore provided, except insofar as he may be directed by the Commission or by a court.

(c) Controlling individual

The books, accounts, memoranda, and records of any person who controls, directly or indirectly, a licensee or public utility subject to the jurisdiction of the Commission, and of any other company controlled by such person, insofar as they relate to transactions with or the business of such licensee or public utility, shall be subject to examination on the order of the Commission.

(June 10, 1920, ch. 285, pt. III, § 301, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 854.)

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions, personnel, property, funds, etc., transferred to Secretary of Energy (except for certain functions which were transferred to Federal Energy Regulatory Commission) by sections 7151(b), 7171(a), 7172(a), 7291, and 7293 of Title 42, The Public Health and Welfare.

Executive and administrative functions of Federal Power Commission, with certain reservations, transferred to Chairman of such Commission, with authority vested in him to authorize their performance by any officer, employee, or administrative unit under his jurisdiction, by Reorg. Plan No. 9 of 1950, §§ 1, 2, eff. May 24, 1950, 15 F.R. 3175, 64 Stat. 1265, set out as a note under section 792 of this title.

SECTION REFERRED TO IN OTHER SECTIONS

This section is referred to in sections 825b, 828b of this title; title 42 section 7172.

§ 825a. Rates of depreciation; notice to State authorities before fixing

(a) The Commission may, after hearing, require licensees and public utilities to carry a proper and adequate depreciation account in accordance with such rules, regulations, and forms of account as the Commission may prescribe. The Commission may, from time to time, ascertain and determine, and by order fix, the proper and adequate rates of depreciation of the several classes of property of each licensee and public utility. Each licensee and public utility shall conform its depreciation accounts to the rates so ascertained, determined, and fixed. The licensees and public utilities subject to the jurisdiction of the Commission shall not charge to operating expenses any depreciation charges on classes of property other than those prescribed by the Commission, or charge with respect to any class of property a percentage of depreciation other than that prescribed therefor by the Commission. No such licensee or public utility shall in any case include in any form under its operating or other expenses any depreciation or other charge or expenditure included elsewhere as a depreciation charge or otherwise under its operating or other expenses. Nothing in this section shall limit the power of a State commission to determine in the exercise of its jurisdiction, with respect to any public utility, the percentage rate of depreciation to be allowed, as to any class of property of such public utility, or the composite depreciation rate, for the purpose of determining rates or charges.

(b) The Commission, before prescribing any rules or requirements as to accounts, records, or memoranda, or as to depreciation rates, shall notify each State commission having jurisdiction with respect to any public utility involved, and shall give reasonable opportunity to each such commission to present its views, and shall receive and consider such views and recommendations.

(June 10, 1920, ch. 285, pt. III, § 302, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 855.)

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions, personnel, property, funds, etc., transferred to Secretary of Energy (except for certain functions which were transferred to Federal Energy Regulatory Commission) by sections 7151(b), 7171(a), 7172(a), 7291, and 7293 of Title 42, The Public Health and Welfare.

Executive and administrative functions of Federal Power Commission, with certain reservations, transferred to Chairman of such Commission, with authority vested in him to authorize their performance by any officer, employee, or administrative unit under his jurisdiction, by Reorg. Plan No. 9 of 1950, §§ 1, 2, eff. May 24, 1950, 15 F.R. 3175, 64 Stat. 1265, set out as a note under section 792 of this title.

SECTION REFERRED TO IN OTHER SECTIONS

This section is referred to in sections 825b, 828b of this title; title 42 section 7172.

§ 825b. Requirements applicable to agencies of United States

All agencies of the United States engaged in the generation and sale of electric energy for ultimate distribution to the public shall be subject, as to all facilities used for such generation and sale, and as to the electric energy sold by such agency, to the provisions of sections 825 and 825a of this title, so far as may be practicable, and shall comply with the provisions of such sections and with the rules and regulations of the Commission thereunder to the same extent as may be required in the case of a public utility.

(June 10, 1920, ch. 285, pt. III, § 303, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 855.)

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions, personnel, property, funds, etc., transferred to Secretary of Energy (except for certain functions transferred to Federal Energy Regulatory Commission) by sections 7151(b), 7171(a), 7172(a), 7291, and 7293 of Title 42, The Public Health and Welfare.

Executive and administrative functions of Federal Power Commission, with certain reservations, transferred to Chairman of such Commission, with authority vested in him to authorize their performance by any officer, employee, or administrative unit under his jurisdiction, by Reorg. Plan No. 9 of 1950, §§ 1, 2, eff. May 24, 1950, 15 F.R. 3175, 64 Stat. 1265, set out as a note under section 792 of this title.

§ 825c. Periodic and special reports; obstructing filing reports or keeping accounts, etc.

(a) Every licensee and every public utility shall file with the Commission such annual and other periodic or special reports as the Commission may by rules and regulations or order prescribe as necessary or appropriate to assist the Commission in the proper administration of this chapter. The Commission may prescribe the manner and form in which such reports shall be made, and require from such persons specific answers to all questions upon which the Commission may need information. The Commission may require that such reports shall include, among other things, full information as to assets and liabilities, capitalization, net investment, and reduction thereof, gross receipts, interest due and paid, depreciation, and other reserves, cost of project and other facilities, cost of maintenance and operation of the project and other facilities, cost of renewals and replacement of the project works and other facilities, depreciation, generation, transmission, distribution, delivery, use, and sale of electric energy. The Commission may require any such person to make adequate provision for currently determining such costs and other facts. Such reports shall be made under oath unless the Commission otherwise specifies.

(b) It shall be unlawful for any person willfully to hinder, delay, or obstruct the making, filing, or keeping of any information, document, report, memorandum, record, or account required to be made, filed, or kept under this chapter or any rule, regulation, or order thereunder.