| Albert Hamilton - 2001 - 624 lapas
...definition: subdividing the major project deliverables into smaller, more manageable components; • activity definition: identifying the specific activities that must be performed to produce the various project deliverables; • activity sequencing: identifying and documenting inter-activity... | |
| David L. Rainey - 2010 - 674 lapas
...mapping of the NPD program is needed. The five key elements for this kind of project mapping are: 11 • Activity definition identifying the specific activities that must be performed to produce the various project deliverables • Activity sequencing identifying and documenting activity dependencies... | |
| Eli Cohen
...Scope Change Control Controlling changes to project scope. N/A 1 2 3 4 5 4. Project Time Management a. Activity Definition Identifying the specific activities...performed to produce various project deliverables. b. Activity Sequencing Identifying and documenting interactivity dependencies. c. Activity Duration... | |
| |