Figure 3.25 shows the same network but with some lead-lag constraints. For example, there is an SS constraint of 2 days and an FF constraint of 2 days between activities A and B. Thus, activity B can start as early as 2 days after activity A starts, but... Industrial Project Management: Concepts, Tools, and Techniques - 104. lappuse autors: Adedeji Badiru, Abidemi Badiru, Adetokunboh Badiru - 2007 - 320 lapas Ierobežota priekšskatīšana -
|