The Law of Government Contracts

Pirmais vāks
J. Byrne, 1927 - 434 lappuses
 

Saturs

Implied Contracts
22
Executed and Executory Contracts
23
Written and Oral or Parol Contracts
24
WHEN A GOVERNMENT CONTRACT IS VALID
25
Validity as Affected by Statute
26
Application of Statute to Contracting Officer
28
Construction of Act by Court of Claims
29
Cases Where the Validity of the Contract is Ques tioned 20 Where Limit of Cost Is Not Fixed
30
Statutes Fixing Limit of Cost
32
Where Contracts Are Implied
34
92
35
Authority May be Inferred from Duties of Officer
36
Appointment of Agents
37
1 Negotiable Paper Not Accepted 26 2 Unauthorized Acts Cannot Establish Usage
38
101
39
CHAPTER PAGE 31 7 Refusal of Superior to Contract Binding on Inferior Officers 32 8 No Implied Contract Exists Where Express One Would be ...
41
Part IIImplied Contracts
43
TORTS AS DISTINGUISHED FROM IMPLIED CONTRACTS
45
Implied Contracts 36 United States Not Liable for Tortious Acts of Its Officers
47
Action for Wrong Done by Agent Not Maintain able Against Government
48
Tortious Acts Recoverable by Suit
49
Fraudulent Taking by Officer and Recovery Therefor
51
Moral Claims Cognizable by Congress 41 Trespass by Government AgentThreatened or Actual
52
When Acceptance is Presumed and Recovery Allowed
54
Caution Necessary as to Implied Contracts
56
Declarations of Emergency Must be in Writing 45 Quartermaster Has No Authority to Contract for Indefinite and Uncertain Amounts or Quantities
57
WHEN A CONTRACT WILL BE IMPLIED
58
Measure of RecoveryImplied Contracts Relating to Personalty
61
Implied Contracts Relating to Real Estate 50 SameWhen Private Property is Used
63
Property Taken Without Occupation 52 Unjust Enrichment Not Applicable to Government 53 Taking by Government Regulations
69
Voluntary Service 55 Evidence of Contract
71
THE IMPLIED CONTRACT TO PAY FOR USE OF PATENTS
72
When Property is Appropriated Compensation is Implied 58 Condition of the Law Prior to 1910
73
The Act Protecting Patentees Construed
74
IMPLIED CONTRACT TO PAY FOR GOODS COMMANDEERED AND COMPENSATION
77
Part IIIPerformance
83
ASSIGNMENT OR TRANSFER OF CONTRACT 65 Prohibitory Statutes
85
Financing the Contract 67 Acquisition of Contract by Reorganization
87
Section 3737 Revised Statutes
88
Leases of Property May Be Transferred 70 The Government May Recognize the Assignment
90
ALTERATIONS AND MODIFICATIONS 71 The Right to Alter 72 Oral Modifications
92
Need of Caution
93
Changes Permissible Without Readvertisement
94
Approval of Officer Designated in Contract Required
95
Changes by Proper Officer Valid as Implied Con tracts
96
Changes Must be Agreed to by Both Parties
97
Rulings as to Extra Work
99
Contractor Should Record Extra Costs
100
CONTRACTS FOR UNCERTAIN QUANTITIES OR INVOLVING UN KNOWN CONDITIONS 80 The Effect of Uncertainty
101
The Phrase More or Less
102
Permissible Variation in Quantity
105
Such Quantity as May be Required
106
Application of Rule to Building Contracts
107
Uncertainty Regarding Conditions to be Encountered 86 Rule as to Measurement in Building Embankment
108
Representations as to Conditions Without Warranty Not Binding
109
Representations as to Conditions Constituting War ranty
111
Specifications Are Binding
114
Measurements Are According to Custom 91 Presumption of Law as to Excess Work
115
Performance Under Coercion by Government Officers
116
TENDER OF PERFORMANCE 93 When Tender Should be Made 94 Reasons Excusing Tender
118
When Tender Is Required
119
Extension of Time of Performance
120
Other Rules of Construction
128
Correspondence a Guide to Correcting Ambiguity
129
Acts of Parties as Basis for Interpretation
130
Clerical Error Is Not Binding 108 Contract and Specifications Irreconcilable Contract Is Void
131
Trade Usage or Custom PAGE
132
APPROVAL OF PERFORMANCE BY OFFICER OR BOARD OF SURVEY
133
Decision of Board if Invoked Is Final
135
Decision of Designated Officer Is Binding
136
Agents Judgment Must be Exercised Reasonably
137
Government Is Bound by Decision of Its Officers
138
The Inspection Officer Should be Clearly Designated
139
Certificate of Approval Necessary to Recovery
140
Approval Not to be Given in Advance of Acceptance
141
Defects Apparent After Acceptance
142
Conclusions to be Drawn
143
The Burden of Notifying the Inspecting Officer 122 Apparent and Latent DefectsFinality of Officers Decision
144
Latent Defects
146
DISPUTES AND COMPROMISES
149
The Rule as to Compromises 126 Principles of Compromise
152
Ruling by the Comptroller
153
Compromises as Result of Mistake
154
STATUTORY PROTECTION OF MATERIAL MEN AND LABORERS
156
Public Work Defined
157
Illustrative Cases
158
Further Interpretation of
166
Part IVBreach
169
WHAT CONSTITUTES BREACH 133 How Breach Arises 134 Acts of Government Which Do Not Constitute Breach
171
Rules of Acceptance Made After the Contract 136 Breach by the United States
173
Breach by the Contractor
177
Waiver of Breach
178
Impossibility of Performance as Excuse for Non Performance
180
Act of God Is Legal Excuse
181
When the Contractor Is Entitled to Damages
193
The Measure of Damages
194
The Case of War Contracts
195
The Treatment of Informal Contracts
198
Interpretation of Act by Courts
200
Arbitration and Award 157 Not All Agreements to Arbitrate Bind
202
Conditions Precedent to Suit
203
What Agreements Will be Sustained 160 What Agreements Will Not be Sustained
204
171
216
CHAPTER PAGE 224 Requirements Contractor Should Remember
224
Consequence of Failure to Obey
225
Quantum Meruit Quantum Valebat Cases Illus trating
226
Act Applies to Emergency Contracts Not Advertised
227
Object of Act to Guide in Its Interpretation
228
Terms of Written Contract Conclusive
229
Preliminary Memoranda_Not Contract
230
Formal Contract Must Follow Accepted Proposal
231
Part VProcedure
237
CHAPTER PAGE XX STATUTORY REQUIREMENTS FOR ADVERTISEMENT
239
GovernmentOwned Corporations
240
Emergency Contracts
244
Necessity of Advertisement 186 Exceptions to the Rule
245
Personal Service 188 Immediate Delivery
246
Public Exigency
247
Military Emergency
248
The Time Element Important
249
Discretionary Powers
250
Other Exceptions
251
Contractor Need Not Advertise 195 Manner of Advertising
252
Various Methods
253
Proposals Addressed to Those Competent to Perform
254
BIDS
255
Opening of Bids and the Award
256
Opening of Bids
257
Right to Modify or Withdraw
258
Irresponsible Bidder May be Rejected
259
Bid Must Conform to Advertisement and Specifi cations
261
When Award Is Not a Contract 206 When Award Is a Contract
262
Notice of Award Must Actually Reach Bidder
264
REFORMATION FOR MISTAKE IN BID
266
Rescission for Error of One Party
267
Reformation and Rescission
268
Opposite Opinions of AttorneyGenerals
270
Contractor Must Exercise Great Care
271
APPROVAL OF SUPERIOR OFFICER
273
When Approval Is Implied 216 Express Approval Should be Secured
274
Ratification by Acquiescence
275
Power of Subordinate Officers to Contract
276
Approval as Distinguished from Ratification
277
FORMAL WRITTEN CONTRACTS
279
Emergency Contracts to be Filed 222 Purpose of the
280
Compliance With
281
Common Law Rule vs Government Contract
287
Need of Caution by Contractor 234 Summary
289
PROCEDURE TO SECURE PAYMENT
290
Settlement of Claims Not Exceeding 1000
292
Laches and Limitations
294
JurisdictionStrict Interpretation of Statute
296
War Emergency Legislation 242 Relief for Moral Claims
297
Arbitration
298
Federal Employees Compensation
299
ATTORNEYS AND THEIR RELATIONS TO GOVERNMENT CONTRACTS 320
300
Acts of Congress Limiting Amount of Contingent Fees
302
APPENDIX
305
General Accounting Office
307
Statutes of General Application
313
Treasury Department
335
District of Columbia Purchases In and For
342
Commerce Department of
345
Labor Department of
347
War Department
351
Navy Department
373
Interior Department of
385
Agriculture Department of
388
Post Office Department
389
Appeals
428
3 How the Executive Authority May Be Exer
27
cisedEffect of Regulations 28 4 Enemy Contracts Are Void 29 5 Recitation of Facts Not Material Does Not Invalidate 30 6 Warning of Lack of Auth...
29
What is Just Compensation? 63 Just CompensationCommandeering Vessels
47
Just Compensation for Merchandise
64
Estimating Profits Upon Abandonment by Sub contractor 162 Breach by Government Justifies Abandonment 163 Result of Abandonment by Contra...
84
DAMAGES 164 Principles Generally Governing 165 Loss Due to Delay Suspension or Abrogation 166 Increased Cost of Labor and Materials Follo...
86
BONDS AND SURETIES 178 Payment of Sureties Performing Work After De fault 179 New Contract by Surety After Default 180 Cases on Suretie...
95
Express and Implied Extensions
97
Acts of Government Constituting Implied Extension
98
Unavoidable and Other Causes of Delays
99
Rule of Law as to Time Limit
100
CONSTRUCTION OR INTERPRETATION OF CONTRACTS 101 General Provisions
101
Contracts Partly Written and Partly Printed
102
Construction by the Parties
103
208
109
231
110
118
118
125
125

Citi izdevumi - Skatīt visu

Bieži izmantoti vārdi un frāzes

Populāri fragmenti

313. lappuse - All purchases and contracts for supplies or services, in any of the Departments of the Government, except for personal services, shall be made by advertising a sufficient time previously for proposals respecting the same, when the public exigencies do not require the immediate delivery of the articles, or performance of the service.
127. lappuse - ... supplies as have been mined or produced in the United States, and only such manufactured articles, materials, and supplies as have been manufactured in the United States...
130. lappuse - The claim that any such testimony or evidence may tend to criminate the person giving such evidence shall not excuse such witness from testifying ; but such evidence or testimony shall not be used against such person on the trial of any criminal proceeding.
333. lappuse - Every claim against the United States, cognizable by the Court of Claims, shall be forever barred unless the petition setting forth a statement thereof is filed in the court, or transmitted to it by the Secretary of the Senate or the Clerk of the House of Representatives as provided Ъу law, within six years after the claim first accrues...
317. lappuse - No contract or purchase on behalf of the United States shall be made unless the same is authorized by law or is under an appropriation adequate to its fulfillment, except in the War and Navy Departments, for clothing, subsistence, forage, fuel, quarters, or transportation, which, however, shall not exceed the necessities of the current year.
125. lappuse - Department under the direction of which said work has been prosecuted that labor or materials for the prosecution of such work has been supplied by him...
315. lappuse - No Executive Department or other Government establishment of the United States shall expend, in any one fiscal year, any sum in excess of appropriations made by Congress for that fiscal year, or involve the Government in any contract or other obligation for the future payment of money in excess of such appropriations unless such contract or obligation is authorized by law.
320. lappuse - It is also further agreed that no Member of or Delegate to Congress, or Resident Commissioner, after his election or appointment, or either before or after he has qualified, and during his continuance in office...
310. lappuse - Congress at the beginning of each regular session, a report in writing of the work of the general accounting office, containing recommendations concerning the legislation he may deem necessary to facilitate the prompt and accurate rendition and settlement of accounts and concerning such other matters relating to the receipt, disbursement, and application of public funds as he may think advisable. In such regular report, or in special reports at any time when Congress is in session, he shall make...
325. lappuse - Columbia, is hereby limited and restricted to eight hours in any one calendar day, and it shall be unlawful for any officer of the United States Government or of the District of Columbia or any such contractor or subcontractor whose duty it shall be to employ, direct, or control the services of such laborers or mechanics to require or permit any such laborer or mechanic to work more than eight hours in any calendar day except in case of extraordinary emergency.

Bibliogrāfiskā informācija