| United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 lapas
...successfully performing the complete work as required. 68. Article 3 of the contract follows : Art. 3. Changes. — The contracting officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general... | |
| United States. Court of Claims - 1948 - 886 lapas
...completion about the end of August 1937. 6. The contract contained the following provisions: ART. 3. Changes. — The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this Contract and within the general... | |
| United States. Court of Claims - 1944 - 960 lapas
...furnished are to be specially manufactured in accordance with Government drawings and specifications, the contracting officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings or specifications, except Government Master Specifications.... | |
| United States. Bureau of Reclamation - 1930 - 132 lapas
...provided. Upon completion of the contract the work shall be delivered complete and undamaged. ARTICLE 3. Changes. — The contracting officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general... | |
| United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 lapas
...provided. Upon completion of the contract the work shall be delivered complete and undamaged. ART. 3. Changes.— The contracting officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general... | |
| United States. Army. Corps of Engineers - 1934 - 396 lapas
...detail drawing and other information as he may consider necessary, unless otherwise provided. ARTICLE 3. Changes. — The contracting officer may at any time, by a written order, and without notice to tho sureties, make changes in the drawings and/or specifications of this contract within the general... | |
| United States. Congress. House. Committee on Military Affairs - 1935 - 812 lapas
...furnished are to be specially manufactured In accordance with Government drawings and specifications, the contracting officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings or specifications. Changes as to shipment and packing of all... | |
| 1939 - 1306 lapas
...he may consider necessary, unless otherwise provided. " Delete all lines which do not apply. ART. 3. Changes. The contracting officer may at any time, by a written order, and without notice to the sureties, make changes In the drawings and/or specifications of this contract within the general scope... | |
| 1939 - 1054 lapas
...executed on standard Government forms. (d) Change orders. Standard contract forms provide that the contracting officer may, at any time, by a written order, and without notice to the sureties, make changes in the drawings and/or specifications, except Federal specifications, and as... | |
| |