Reactor Safety Issues at Department of Energy Facilities: Hearing Before the Committee on Governmental Affairs, United States Senate, One Hundredth Congress, First Session, March 12, 1987, 4. sējums

Pirmais vāks
U.S. Government Printing Office, 1987 - 414 lappuses
 

Citi izdevumi - Skatīt visu

Bieži izmantoti vārdi un frāzes

Populāri fragmenti

61. lappuse - I would be pleased to respond to any questions you or members of the committee may have.
106. lappuse - He is a fellow of the American Physical Society and the American Institute of Aeronautics and Astronautics.
241. lappuse - These items would normally arise in the Probability Risk Assessment (PRA) level 3 study recommended by the Design Team which study should be expedited. These items which I believe should be completed within one year and before the PRA is completed are: 1. Study the possible effects of a longitudinal split type break in an embrittled Zirconium alloy process tube within the graphite. If such a break can lead to stresses on adjacent tubes which can propagate in the core then something like the Chernobyl...
93. lappuse - Safeguards (ACRS) is a statutory committee established to advise the Commission on the safety aspects of proposed and existing nuclear facilities and the adequacy of proposed reactor safety standards, and to perform such other duties as the Commission may request.
6. lappuse - DOE develop a comprehensive strategy that sets forth the projected facility requirements for continued nuclear weapons production; a comprehensive picture of the environmental, safety, and health issues facing DOE; and solutions to resolve them. The...
105. lappuse - School of Engineering and Applied Science, at the University of California, Los Angeles, where he has served since 1971.
232. lappuse - SCOPE OF REPORT: As one of six individual consultants asked to make recommendations on the "N" reactor in the light of the Chernobyl-4 accident this report is submitted. Appendix 1 contains the charge letter and my qualifications. The other appendices include a bibliography and the list of joint briefings and special meetings. The discussion, conclusions and recommendations below are based on the material and meetings listed therein and on my experiences in the nuclear power area since 1946.
93. lappuse - Engineering, School of Engineering and Applied Science, University of California, Los Angeles, California Mr.
47. lappuse - Mr. J. Dexter Peach Assistant Comptroller General, Resources, Community, and Economic Development Division US General Accounting Office Washington, DC 20548 Dear Mr. Peach: This is the Department of Defense (DoD) response to the General Accounting Office (GAO) draft report, "AIRSPACE USE: FAA Needs to Improve Its Management of Special Use Airspace," dated April l9, l988 (GAO Code 34ll63), OSD Case 7620.
359. lappuse - Following the accident at the Chernobyl Nuclear Power Plant in the Soviet Union...

Bibliogrāfiskā informācija