... task needed to install , test , align , operate and remove the MILES M1 equipment . A special index precedes each set of tasks . These can be used as checklists to ensure that all tasks have been completed . NOTE Unless otherwise ...
... task needed to install , test , align , operate and remove the MILES M1 equipment . A special index precedes each set of tasks . These can be used as checklists to ensure that all tasks have been completed . NOTE Unless otherwise ...
1-1. lappuse
... tasks , ask your NCO or instructor to show you how . When you can do all these tasks , go on with this manual . Purpose of Equipment . MILES equipment for the M1 Abrams 1-1 TM 9-1265-373-10-1 CHAPTER SECTION INTRODUCTION General ...
... tasks , ask your NCO or instructor to show you how . When you can do all these tasks , go on with this manual . Purpose of Equipment . MILES equipment for the M1 Abrams 1-1 TM 9-1265-373-10-1 CHAPTER SECTION INTRODUCTION General ...
2-2. lappuse
... Tasks 9 , 11 , and 13 Inside Tasks 2 , 4 , 6 , 8 , and 10 M2 Machine Gun Task 2 M240 Machine Gun Task 2 MWLD Tasks 3 and 4 Postoperational Task 7 ( Table 2-2 . Operator / Crew Preventive Maintenance Checks and 2-2 TM 9-1265-373-10-1 ...
... Tasks 9 , 11 , and 13 Inside Tasks 2 , 4 , 6 , 8 , and 10 M2 Machine Gun Task 2 M240 Machine Gun Task 2 MWLD Tasks 3 and 4 Postoperational Task 7 ( Table 2-2 . Operator / Crew Preventive Maintenance Checks and 2-2 TM 9-1265-373-10-1 ...
2-4. lappuse
... tasks . While some crew members are performing one set of tasks , others can be performing another set . Before you begin , read all steps in the task and look at each drawing carefully . To help perform a task , most steps have ...
... tasks . While some crew members are performing one set of tasks , others can be performing another set . Before you begin , read all steps in the task and look at each drawing carefully . To help perform a task , most steps have ...
2-5. lappuse
INDEX OF TASKS Preinstallation Task Outside Tasks Inside Tasks Page 2-5 2-6 2-28 M2 Machine Gun Tasks 2-46 M240 Machine Gun Tasks 2-51 MWLD Tasks 2-56 Test Tasks 2-63 Alignment Tasks 2-68 Operation Tasks Postoperational and Storage Tasks ...
INDEX OF TASKS Preinstallation Task Outside Tasks Inside Tasks Page 2-5 2-6 2-28 M2 Machine Gun Tasks 2-46 M240 Machine Gun Tasks 2-51 MWLD Tasks 2-56 Test Tasks 2-63 Alignment Tasks 2-68 Operation Tasks Postoperational and Storage Tasks ...
Citi izdevumi - Skatīt visu
Bieži izmantoti vārdi un frāzes
alarm Align Subtask Ask controller attached battery box blank ammunition blank fire blank fire adapter Blank Fire Attachment boresight target breech BUSINESS REPLY MAIL bustle rack cable labeled coax machine gun COMPONENTS OF END connector Cont control console controller key CVKI Cable Assembly CVKI light detector belt segments display window dry fire END ITEM ENTER key 11 fastener tape Fluid Ounces Helmet Harness Hoffman device Inches Inside Subtask Inside Task Inspect and Service intercom loader's hatch M1 Abrams Tank M1 Tank M2 Machine Gun M2 MG M240 machine M240 MG Task machine gun transmitter main gun Meters MG Laser Transmitter MG Transmitter microphone MILES cables MILES equipment MILES system mm/Coax mounting MWLD Task National Stock Number opposing fire Postoperational and Storage Postoperational Tasks Press ENTER key prevent normal operation receptacle reloading Report any damage Simulator System Storage Task Subtask 1-A Test Subtask torso harness Troubleshooting turn turret window 9