Cases Decided in the Court of Claims of the United States, 103. sējumsU.S. Government Printing Office, 1946 |
No grāmatas satura
1.5. rezultāts no 100.
63. lappuse
... plaintiff's bid on September 22 , 1936 , plaintiff learned that there was a wide difference be- tween the amount of its bid and the amount of the Govern- ment engineer's estimate for the work , and plaintiff's Presi- dent and Col. Park ...
... plaintiff's bid on September 22 , 1936 , plaintiff learned that there was a wide difference be- tween the amount of its bid and the amount of the Govern- ment engineer's estimate for the work , and plaintiff's Presi- dent and Col. Park ...
68. lappuse
... Plaintiff actually cleared 3,733.23 acres . Included in this total number of acres were the 1,446 acres described above . 10. As the work progressed plaintiff was paid either monthly or semimonthly by voucher upon each of which was ...
... Plaintiff actually cleared 3,733.23 acres . Included in this total number of acres were the 1,446 acres described above . 10. As the work progressed plaintiff was paid either monthly or semimonthly by voucher upon each of which was ...
94. lappuse
... plaintiff's claim , show that Claim 1 made by plaintiff , which was the only claim allowed by the con- tracting officer for additional compensation , measured by the difference between $ 78 an acre and its bid price of $ 51.85 an acre ...
... plaintiff's claim , show that Claim 1 made by plaintiff , which was the only claim allowed by the con- tracting officer for additional compensation , measured by the difference between $ 78 an acre and its bid price of $ 51.85 an acre ...
95. lappuse
... plaintiff's claim that as to these areas it had been misled . These rulings as to what was required of plaintiff by the contract specifications meant that plaintiff was to clear all areas between 244 and 260 feet whether within or ...
... plaintiff's claim that as to these areas it had been misled . These rulings as to what was required of plaintiff by the contract specifications meant that plaintiff was to clear all areas between 244 and 260 feet whether within or ...
96. lappuse
... Plaintiff does not here question that phase of the decision and the defendant cannot rely upon that part of it as a means of rejecting the findings and decision on the other questions of fact . About two weeks after plaintiff started ...
... Plaintiff does not here question that phase of the decision and the defendant cannot rely upon that part of it as a means of rejecting the findings and decision on the other questions of fact . About two weeks after plaintiff started ...
Citi izdevumi - Skatīt visu
Bieži izmantoti vārdi un frāzes
acres Act of June agreement amount approved August August 11 back counters building caisson cents change order Chickasaw Nation Chief of Engineers Choctaw cofferdam Commissioner Company completed concrete Congress construction contracting officer contractor corporation Creek cubic yards December decision defendant defendant's delay drawings dredging employees Engineer entitled to recover excavation filed findings of fact Five Civilized Tribes flour follows funds gift gift tax Government Honduras included income Industrial Recovery Act Judge July June 16 labor lands letter liquidated damages mails March material Medric ment National Industrial Recovery Navy November November 9 October Opinion original Indian title overdepth paid paragraph payment period petition plaintiff proof purchase referred refund Reporter's Statement reservation River rock Secretary Section September shown specifications Stat thereof Tillamooks Tillamooks tribe tion Too-too-to-ney tract tribes and bands trust unratified treaty vessel wages
Populāri fragmenti
5. lappuse - But no such damages shall be adjusted and paid until thoroughly examined and passed upon by the Commissioner of Indian Affairs and the Secretary of the Interior...
65. lappuse - ... due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to such causes...
433. lappuse - Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern.
681. lappuse - Officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract.
575. lappuse - Section 2512 provides that if a gift is made in property, its value at the date of the gift shall be considered the amount of the gift.
289. lappuse - In addition to other taxes, there is hereby Imposed on every employer an excise tax, with respect to having individuals in his employ...
492. lappuse - Nebraska, or to affect the authority of the government of the United States to make any regulation respecting such Indians, their lands, property, or other rights, by treaty, law, or otherwise, which it would have been competent to the government to make, if this act had never passed.
254. lappuse - Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.
579. lappuse - ... unless before the expiration of such period a claim therefor is filed by the taxpayer.
108. lappuse - CHANGES The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following...