" CHANGES The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following... "
The Code of Federal Regulations of the United States of America - 17. lappuse
1949
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 120-130. sējumi

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 lapas
...are believed to be approximately correct. ***** The contract provided in part as follows : ARTICLE 3. Changes. — The contracting officer may at any...such changes cause an increase or decrease in the amout due under this contract ,or in the time required for its performance, an equitable adjustment...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 114. sējums

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 lapas
...specifically provided for in the contract. The contract contained the following provisions : ARTICLE 3. Changes. — The contracting officer may at any...thereof. If such changes cause an increase or decrease 571 Reporter's Statement of the Case in the amount due under this contract, or in the time required...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 119. sējums

United States. Court of Claims, Audrey Bernhardt - 1951 - 968 lapas
...copy was sent to it on February 26, 1943. 5. Pertinent provisions of the contract provided : ARTICLE 3. Changes, — The contracting officer may at any...specifications of this contract and within the general scope 707 ~ - ' - Findings of F!«t thereof. If such changes cause an increase or decrease in the amount...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 121. sējums

United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 lapas
...Judge; WHITAKER, Judge; LITTLETON, Judge; and JONES, Chief Judge, concur. * Article S. Change*. — The contracting officer may at any time, by a written...contract and within the general scope thereof. If inch changes cause an Increase or decrease In the amount due under this contract, or In the time required...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 132. sējums

United States. Court of Claims, Audrey Bernhardt - 1955 - 936 lapas
...61,200 Cu. yd 3 62 Findings of Fact as he may consider necessary, unless otherwise provided. ARTICLE 3. Changes. — The contracting officer may at any...the drawings and/or specifications of this contract within the general scope thereof. If such changes cause increase or decrease in the amount due under...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 109. sējums

United States. Court of Claims - 1948 - 974 lapas
...printed in a footnote,1 or by reason of a mutual mistake of fact, or for 1 ARTICLE 3. Changet. — The contracting officer may at any time, by a written...the drawings and/or specifications of this contract within the general scope thereof. If such changes cause an Increase or decrease in the amount due under...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 118. sējums

United States. Court of Claims, Audrey Bernhardt - 1951 - 840 lapas
...-which amount was paid to plaintiff. 3. The contract provided, among other things, as follows: ARTICLE 3. Changes. — The Contracting Officer may at any...the sureties, make changes in the drawings and/or specification of this Contract and within the general scope thereof. If such changes cause an increase...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 111. sējums

United States. Court of Claims - 1948 - 886 lapas
...188 days at $25 per day, or a total of $4,700. 9. The contract provided, in part, as follows : ART. 3. Changes. — The contracting officer may at any...notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general scope thereof. If such changes cause...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 116. sējums

United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 lapas
...and Consolidated Builders, Inc., as CBI 14. Certain articles of the contract read as follows : ART. 3. Changes. — The contracting officer may at any...notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general scope thereof. If such changes cause...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 95. sējums

United States. Court of Claims - 1942 - 868 lapas
...expediting construction. Reporter's Statement of the Case 9. Article 3 of the contract reads as follows : Changes. — The contracting officer may at any time,...notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general scope thereof. If such changes cause...