" The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor... "
The Code of Federal Regulations of the United States of America - 51. lappuse
1949
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 145. sējums

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 lapas
...providing that the contractor should not be charged with liquidated damages "because of any delays * * * due to unforeseeable causes beyond the control and...acts of God * * * acts of the Government, acts of another contractor in the performance of a contract with the Government, * * * and unusually severe...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 109. sējums

United States. Court of Claims - 1948 - 974 lapas
...Provided further, That the contractor shall not be charged with liquidated damages or any exo-oS cost when the delay is due to unforeseeable causes beyond...contractor, including but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes,...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 93. sējums

United States. Court of Claims - 1941 - 858 lapas
...contractor would not be charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and...restricted to, acts of God, acts of the Government, strikes, and unusually severe weather. This article further provided that "the contractor shall within...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 106. sējums

United States. Court of Claims - 1946 - 936 lapas
...contractor shall not be charged with liquidated damages or any excess cost when the delay in delivery is due to unforeseeable causes beyond the control...contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes,...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 108. sējums

United States. Court of Claims - 1947 - 828 lapas
...the contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and...contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 105. sējums

United States. Court of Claims - 1946 - 920 lapas
...the contractor shall not be charged liquidated damages because of any delay in completion of the work due to unforeseeable causes beyond the control and...contractor, including but not restricted to acts of the Government, acts of another contractor in performance of a contract with the Government, etc. It...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 111. sējums

United States. Court of Claims - 1948 - 886 lapas
...shall not be charged with any excess cost * * * when the delay of the contractor in making deliveries is due to unforeseeable causes beyond the control...of the contractor, including, but not restricted to * * * unusually severe weather * * *. The contracting officer shall then ascertain the facts and extent...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 122. sējums

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 lapas
...any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of Ood, or of the public enemy, acts of the Government including, but not restricted to any preference,...
Pilnskats - Par šo grāmatu

Decisions of the Comptroller General of the United States, 23. sējums

United States. General Accounting Office - 1944 - 1220 lapas
...supplies in the open market or under other contracts when the delay of the contractor in making deliveries is due to unforeseeable causes beyond the control...contractor, including, but not restricted to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...
Pilnskats - Par šo grāmatu

Decisions of the Comptroller General of the United States, 29. sējums

United States. General Accounting Office - 1950 - 710 lapas
...contractor shall not be charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and...the contractor, including, but not restricted to, the causes specified therein. Thus, regardless of whether the cause of delay occurs before or after...