" ... the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise,... "
Investigation of Military Public Works: Hearings Before a Subcommittee of ... - 322. lappuse
autors: United States. Congress. House. Committee on Appropriations - 1952
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 128. sējums

United States. Court of Claims, Audrey Bernhardt - 1954 - 918 lapas
...which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor...sureties shall be liable to the Government for any excess cost occasioned the Government thereby. If the contractor's right to proceed is so terminated, the...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 109. sējums

United States. Court of Claims - 1948 - 974 lapas
...the work or such part of the work as to which there has been a failure to pay said required wages and prosecute the work to completion by contract or otherwise,...the contractor and his sureties shall be liable to trie Government for any excess costs occasioned the Government thereby. 4. Before bidding, plaintiff...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 101. sējums

United States. Court of Claims - 1944 - 960 lapas
...to proceed and in this connection the contract provided that the Government might complete the work, by contract or otherwise, "and the contractor and...sureties shall be liable to the Government for any excess cost occasioned the Government thereby." By terminating the contractor's right to proceed the Government...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 148. sējums

United States. Court of Claims, Audrey Bernhardt - 1962 - 784 lapas
...market or secure the manufacture and delivery of the materials and supplies by 49 Finding* of Fact contract or otherwise, and the contractor and his...sureties shall be liable to the Government for any excess cost occasioned the Government thereby : * * * 41. Prior to termination of the contract, a representative...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 120-130. sējumi

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 lapas
...which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his sureties shall be liable to the Qovernment for any excess cost occasioned the Government thereby. If the contractor's right to proceed...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 111. sējums

United States. Court of Claims - 1948 - 886 lapas
...or supplies in the open market or secure the manufacture and delivery of the materials and supplies by contract or otherwise, and the contractor and his sureties shall be liable to the Government thereby; Provided, that the contractor shall not be charged with any excess cost occasioned the Government...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 83. sējums

United States. Court of Claims - 1937 - 786 lapas
...work the Government has the right to terminate the contract, take over the work and prosecute the same to completion by contract or otherwise and the contractor and his sureties shall be liable for any excess cost occasioned the Government thereby. The second course the Opinion of the Court Government...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 104. sējums

United States. Court of Claims - 1946 - 936 lapas
...event the original contractor defaulted and the Government completed the work by contract or otherwise, "the contractor and his sureties shall be liable to the Government for any excess cost occasioned the Government thereby." Art. 15 made the decisions of the contracting officer and...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 132. sējums

United States. Court of Claims, Audrey Bernhardt - 1955 - 936 lapas
...which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his sureties shall 645 _ Findings of Fact be liable to the Government for any excess cost occasioned the Government thereby....
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 103. sējums

United States. Court of Claims - 1946 - 906 lapas
...which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his sureties (if any) shall be liable to the Government for any excess cost occasioned the Government thereby. If...