| United States. Court of Claims, Audrey Bernhardt - 1949 - 832 lapas
...the case of a contract made by the District of Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty, and...contractor or subcontractor may, within six months after decision by such head of a department or the Commissioners of the District of Columbia, file a claim... | |
| United States. Congress. House. Committee on Labor - 1904 - 486 lapas
...Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty; and from such final order whereby a contractor or subcontractor...hereinbefore provided such contractor or subcontractor may appeal to the Court of Claims, which shall have jurisdiction to hear and decide the matter in like... | |
| United States. Congress. Senate. Committee on Education and Labor - 1904 - 248 lapas
...the action imposing the penalty, and from such final order whereby a contractor or sub3 contractor may be aggrieved by the imposition of the penalty...hereinbefore provided such contractor or subcontractor may appeal to the Court of Claims, which shall have jurisdiction to hoar and decide the matter in like... | |
| United States. Congress. House. Committee on Labor - 1904 - 212 lapas
...Commissioners thereof, who shall have power to review the action imposing the penalty, and from that final order whereby a contractor or subcontractor may be aggrieved by the imposition of the penalty provided, such contractor or subcontractor may appeal to the Court of Claims. Mr. GILBERT. Did you... | |
| United States. Congress. House. Labor Committee - 1905 - 144 lapas
...Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty; and from such final order whereby a contractor or subcontractor...hereinbefore provided such contractor or subcontractor may appeal to the Court of Claims, which shall have jurisdiction to hear and decide the matter in like... | |
| United States. Department of Commerce and Labor - 1905 - 154 lapas
...Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty; and from such final order whereby a contractor or subcontractor...hereinbefore provided such contractor or subcontractor may appeal to the Court of Claims, which shall have jurisdiction to hear and decide the matter in like... | |
| United States. Congress. House. Labor Committee - 1906 - 228 lapas
...Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty, and from such final order whereby a contractor or subcontractor...hereinbefore provided, such contractor or subcontractor may appeal to the Court of Claims, which shall have jurisdiction to hear and decide the matter in like... | |
| United States. Congress. House. Committee on Labor - 1906 - 226 lapas
...,»hall hare potrer to rericir the action imposing the penalty; and from such ftniil order irhereby я contractor or subcontractor may be aggrieved by the imposition of the penalty hereinbefore prorulcd such contractor or subcontractor may appeal to the Court of Claims, which shall have jurisdiction... | |
| United States. Congress. House. Committee on Labor - 1908 - 1016 lapas
...Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty, and from such final order whereby a contractor or subcontractor may be aggrieved by the imposition oí tin; penalty heroiubefore provided such contractor or subcontractor may appeal to the Court of... | |
| 1912 - 1652 lapas
...the case of a contract made by the District of Columbia to the Commissioners thereof, who shall have power to review the action imposing the penalty, and...contractor or subcontractor may within six months after decision by such head of a department or the Commissioners of the District of Columbia file a claim... | |
| |