" That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion, of the work due to unforeseeable causes beyond the control and without the fault or negligence... "
The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ... - 77. lappuse
autors: Ray Lyman Wilbur, United States. Department of the Interior, Elwood Mead - 1933 - 120 lapas
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 87. sējums

United States. Court of Claims - 1939 - 836 lapas
...the defendant. SECOND CAtJSE OF ACTION Article 9 of the contract is in part as follows : Provided, That the right of the contractor to proceed shall...unforeseeable causes beyond the control and without the fault or negligence 0r the contractor, including, but not restricted to, acts of God * * *. The contract...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 111. sējums

United States. Court of Claims - 1948 - 886 lapas
...liquidated damages for delay in completing the work and contained the following proviso : Provided, That the right of the contractor to proceed shall...unforeseeable causes beyond the control and without the fault or negligence of the con552 Reporter's Statement of the Case tractor, including, but not restricted...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 114. sējums

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 lapas
...delays resulted from certain specified causes stated in Article 9 of the contract as follows : * * * the right of the contractor to proceed shall not be...unforeseeable causes beyond the control and without the fault or negligence ol the contractor, including, but not restricted to, acts of God, or 114 C. Cls....
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 104. sējums

United States. Court of Claims - 1946 - 936 lapas
...contract referred to in the section of the specifications just quoted was as follows: * * * Provided, That the right of the contractor to proceed shall...completion of the work due to unforeseeable causes 104 C. CU. Reporter's Statement of the Caie beyond the control and without the fault or negligence...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 105. sējums

United States. Court of Claims - 1946 - 920 lapas
...accompanying papers and the contractor and his sureties shall be liable for the amount thereof: Provided, That the right of the contractor to proceed shall...of any delays in the completion of the work due to unfore116 Reporter's Statement of the Case seeable causes beyond the control and without the fault...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 125. sējums

United States. Court of Claims, Audrey Bernhardt - 1958 - 1004 lapas
...as required under Article 9 of the contract. This article reads in part as follows : * * * Provided, That the right of the contractor to proceed shall...because of any delays in the completion of the work * * * if the contractor shall within 10 days from the beginning of any such delay * * * notify the...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 94. sējums

United States. Court of Claims - 1942 - 818 lapas
...— (Excerpt from) "Provided, That the right of the contractor to proceed shall not be determinated or the contractor charged with liquidated damages...unforeseeable causes beyond the control and without the fault or negligence of the contractor." The above quotation would be a very fair one to apply to our...
Pilnskats - Par šo grāmatu

Cases Decided in the Court of Claims of the United States, 98. sējums

United States. Court of Claims - 1943 - 906 lapas
...* * * liquidated damages for each calendar day of delay," but with the proviso that he shall not be "charged with liquidated damages because of any delays...unforeseeable causes beyond the control and without the fault or negligence of the contractor * * *." The contracting officer's findings are challenged by...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 122. sējums

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 lapas
...accompanying papers and the Contractor and his sureties shall be liable for the amount thereof; Provided, That the right of the Contractor to proceed shall...Contractor charged with liquidated damages because of any delay in the completion of the work due to unforeseeable causes beyond the control and without the...
Pilnskats - Par šo grāmatu

Cases Decided in the United States Court of Claims ... with ..., 116. sējums

United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 lapas
...* Provided, That the right of the contractor to proceed shall not be terminated under this Article or the contractor charged with liquidated damages...completion of the work due to unforeseeable causes be891357—50 25 Reporter's Statement of the Case yond the control and without the fault or negligence...